relocation canal update

April 25, 2019.

The damage was more extensive than originally thought. Crews have been working overtime since the washout occurred. There was one concrete pour yesterday, and there will be another one today. That concrete has to cure before we can make the final pour.

Originally, we had hoped to put a coffer in the canal and deliver water for one day to RL-1 and RL-2 (Division St. Pump Station). However, we cannot risk that water getting by and damaging the work we are doing, so we will not be attempting this.

Our new target for delivering water down the Relocation Canal is Tuesday, April 30.