**UPDATE** MAIN CANAL OUTAGE

May 29, 2019 9:45 am

Crews were on site at 6:00 am this morning. There are 2 panels that need to be replaced. Concrete is coming in this afternoon. FORECAST: Turning water back into the Main Canal Thursday afternoon.

May 28, 2019 11:50 am

During their morning run, ditchriders noticed a washout near our spill gate by the siphon going under the freeway. We shut water off at the dam and stopped diverting water into Boardman, and are draining the canal. Once the canal is drained, the repair can be done. We have hired Wesley Wise Excavating to do the repair.

Water should be back in the canal at the end of the week. Watch here for updates. If you have questions, please call the office at 541-922-3814.