4/9 WATER UPDATE

The siphon repairs are complete and water is flowing into Boardman. Crews will finish burning the laterals and start opening up the pump stations Thursday and Friday.

Sunrise Pump Station remains under construction. We are waiting on the electrician to rewire the meter base, and on contractor scheduling.

In irrigon, several areas are without water due to breaks in the lines. There are 3 separate problems, affecting about 50% of the people. We hope to have everything up sometime Saturday.